SSC Cashflow and NPV Models
===========================
Imagine a portfolio of candidate projects, in which some of the decisions involve
either replacing an item now or postponing replacement and facing potentially higher
maintenance and replacement costs. We assume the item must either be replaced now or
in the future, and it is in this context that we describe the appropriate cashflow
calculations. We then extend the discussion to allow the planned replacement to occur
in year 2 or 3, rather than in year 1.
We assume that doing nothing is not an option, since the items under consideration
are of significant importance and, if not replaced in due course, would impose an
unacceptable risk to either safety or production.
Notation:
- :math:`p`: probability of item failure for one year
- :math:`C_P`: cost of planned replacement
- :math:`C_U`: cost of unplanned replacement
- :math:`C_D`: cost of shutdown per day
- :math:`D`: number of days plant is off-line, if a shutdown occurs
- :math:`N`: number of years
- :math:`R`: discount rate
We could incorporate additional parameters, such as weekly or monthly inspection costs,
fixed costs of shutdown in addition to the daily costs specified above, etc. The setting
we describe allows us to illustrate key ideas in the cashflow calculations for computing NPV.
We further assume that, if we do not replace the item, its failure time is a random
variable following a geometric distribution where the probability of failure in
one year is :math:`p` (i.e., probability of survival over one year is :math:`1-p`).
Thus, if the plant faces a 20-year decision period, the probability of survival to year
:math:`t` is :math:`(1-p)^t`, and the probability of failing in year :math:`t` is
:math:`p(1-p)^{t-1}`.
A useful construct for the calculations is to visualize a *coin flip* for each year,
yielding a *fail* or *no fail* event, and immediately after the flip appropriate
costs are incurred.
If the item is not replaced today (:math:`t=1`), the expected replacement cost in any
year :math:`t = 1,2,\ldots,N-1` is:
.. math::
:label: npv_1
\text{Expected Replacement Cost in Year } t =
C_U \, p (1-p)^{t-1}
Here, we incur this cost only if the item survived years :math:`1` to :math:`t-1`
and failed in year :math:`t`.
Since we assume the item must be replaced in year :math:`N` if it has not already
failed, the expected replacement cost in year :math:`N` is:
.. math::
:label: npv_2
\text{Expected Replacement Cost in Year } N =
C_P (1-p)^{N-1}
To illustrate downtime, assume shutdown costs of :math:`C_D` per day. The expected
downtime cost in year :math:`t=1,\ldots,N-1` is:
.. math::
:label: npv_3
\text{Expected Downtime Cost in Year } t =
D\,C_D \, p (1-p)^{t-1}
More generally, we can express reliability-related costs with:
.. math::
Re\_Cost(p, t, C_1, C_2, \ldots, C_M)
There are two relevant time-series of cash flows: replacing now and replacing later.
If replaced today (time :math:`t=1`), we incur the planned replacement cost
:math:`C_P`.
For replacing later, for :math:`t = 1,\ldots,N-1`, the expected cash flows are:
.. math::
:label: npv_4
\text{Cash Flow Replaced in Year } t =
-\left[(C_U + D C_D) \, p \, (1-p)^{t-1} \right]
And for the final year:
.. math::
:label: npv_5
\text{Cash Flow Replaced in Year } N =
-\left[ C_P (1-p)^{N-1} \right]
All cash flows are costs and therefore negative.
.. figure:: ../figures/image1.png
:scale: 100%
:alt: Replace now timeline
Graphical representation of option 1: replace now.
.. figure:: ../figures/image2.png
:scale: 100%
:alt: Replace later timeline
Graphical representation of option 2: replace later.
The NPV of option 1 is:
.. math::
:label: npv_6
\text{NPV option 1} = -C_P
The NPV of option 2 is:
.. math::
:label: npv_7
\text{NPV option 2} =
-\left[
\sum_{t=1}^{N-1}
\frac{(C_U + D C_D) p (1-p)^{t-1}}{(1+R)^{t-1}}
+
\frac{C_P (1-p)^{N-1}}{(1+R)^{N-1}}
\right]
The difference between the two NPVs is:
.. math::
:label: npv_7_b
\text{NPV} =
-C_P +
\left[
\sum_{t=1}^{N-1}
\frac{(C_U + D C_D) p (1-p)^{t-1}}{(1+R)^{t-1}}
+
\frac{C_P (1-p)^{N-1}}{(1+R)^{N-1}}
\right]
If :math:`\text{NPV} > 0`, the decision is to replace today.
Planned Replacement at :math:`T_0`
----------------------------------
Now we allow delaying planned replacement to year :math:`T_0`, at the risk of
possible failure before then.
For :math:`t = 1,\ldots,T_0 - 1`, the cash flow is:
.. math::
:label: npv_8
\text{Cash Flow Replaced in Year } t =
-\left[(C_U + D C_D) p (1-p)^{t-1}\right]
For :math:`t = T_0`, the expected planned replacement cash flow is:
.. math::
:label: npv_9
\text{Cash Flow Replaced in Year } T_0 =
-\left[ C_P (1-p)^{T_0 - 1} \right]
.. figure:: ../figures/image3.png
:scale: 100%
:alt: Planned replacement at T0
Graphical representation of option 1: planned replacement at :math:`T_0`.
The NPV for planned replacement at :math:`T_0` is:
.. math::
:label: npv_10
\text{NPV option 1} =
-\left[
\sum_{t=1}^{T_0-1}
\frac{(C_U + D C_D) p (1-p)^{t-1}}{(1+R)^{t-1}}
+
\frac{C_P (1-p)^{T_0-1}}{(1+R)^{T_0-1}}
\right]
If :math:`T_0 = 1`, this reduces to :math:`-C_P`.
Option 2 (delay to :math:`N`) has NPV:
.. math::
:label: npv_11
\text{NPV option 2} =
-\left[
\sum_{t=1}^{N-1}
\frac{(C_U + D C_D) p (1-p)^{t-1}}{(1+R)^{t-1}}
+
\frac{C_P (1-p)^{N-1}}{(1+R)^{N-1}}
\right]
Thus, the incremental NPV is:
.. math::
:label: npv_12
\text{NPV} =
\sum_{t=T_0}^{N-1}
\frac{(C_U + D C_D) p (1-p)^{t-1}}{(1+R)^{t-1}}
+
\frac{C_P (1-p)^{N-1}}{(1+R)^{N-1}}
-
\frac{C_P (1-p)^{T_0-1}}{(1+R)^{T_0-1}}
A new RAVEN **External Model** with ``subType="LOGOS.IncrementalNPV"`` is used to
compute the NPVs described above.
Example RAVEN Input XML
-----------------------
.. code-block:: xml
fp,rvi_npv_a,rvi_npv_b
fp
19.82
39.64
0.05
1.
30
| 1, 4 |
0.03
2019
20
External Model Parameters
-------------------------
- ``Cp``: float, required – cost of planned replacement
- ``Cu``: float, required – cost of unplanned replacement
- ``Cd``: float, required – cost of shutdown per day
- ``D``: integer, required – days plant is off-line
- ``fp``: float, required – probability of item failure over one year
- ``discountRate``: float, required – discount rate
- ``inflation``: float, optional (default 0.0)
- ``tax``: float, optional (default 0.0)
- ``HardSavings``: float, optional (default 0.0)
- ``count``: int, optional (default 1)
- ``startTime``: int, required
- ``lifetime``: int, required
Options:
- ``Td``: comma-separated integers specifying delay lengths
- ``output``: output variable names (must appear under ````)
The parameters ``Cp, Cu, fp, Cd, inflation, tax`` may be sampled by RAVEN. If
specified in the XML, they are replaced by sampled values.
Example Incremental NPV Output CSV
----------------------------------
.. code-block:: none
fp,rvi_npv_a,rvi_npv_b
...
.. note::
The TEAL plugin is required to compute NPVs.
See: https://github.com/idaholab/raven/wiki/Plugins
.. figure:: ../figures/image11.jpg
:scale: 50%
:alt: RAVEN Logos workflow
Risk-informed capital budgeting via RAVEN and RAVEN plugins.